VY decommissioning by the numbers

VERNON — Cost projections from new filings by NorthStar Group Services Inc., the proposed buyer of the Vermont Yankee nuclear plant in Vernon:

• $811.5 million: Total costs at Vermont Yankee from 2019 to 2052

• $511.1 million: Nuclear Regulatory Commission license termination costs

• $287.8 million: Spent nuclear fuel management

• $12.6 million: Site restoration

• $17 million: Amount expected to remain in trust accounts after cleanup